LIST OF ATTEMPTED QUESTIONS AND ANSWERS
 Select The Blank
  Question 
The ________ must ensure that the product satisfy the functional requirements of it's usage.
  Correct Answer 
Quality of design
  Your Answer 
Quality of design
 Multiple Choice Multiple Answer
  Question 
Which of the following information is available in summary of part in a chart during methods study?
  Correct Answer 
Frequency of each symbol , Total time for each symbol , Total distance travelled by the object
  Your Answer 
Frequency of each symbol , Total time for each symbol
 True/False
  Question 
The event numbers as far as possible reflect the logical relationships of the activities.
  Correct Answer 
True
  Your Answer 
False
 Multiple Choice Single Answer
  Question 
Which varaible is taken along the ordinate or Y axis?
  Correct Answer 
Quality
  Your Answer 
Quality
 Multiple Choice Multiple Answer
  Question 
Which of the following schedules are recommended to prepare and follow as a part of preventive maintenance system?
  Correct Answer 
Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule
  Your Answer 
Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule
 Multiple Choice Single Answer
  Question 
Which kind of preventive inspection detects some maintenance related characteristics by making use of human senses, when equipment is in operation?
  Correct Answer 
Extrernal inspection
  Your Answer 
Extrernal inspection
 Multiple Choice Multiple Answer
  Question 
Which are different ways to show critical path in a network?
  Correct Answer 
Thick Line , Red Line , Double Line
  Your Answer 
Thick Line , Red Line , Double Line
 Multiple Choice Multiple Answer
  Question 
What are the benefits of overhauling?
  Correct Answer 
It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares
  Your Answer 
It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares
 Match The Following
Question
Correct Answer
Your Answer
Combined Layout
Mixed Layout
Mixed Layout
Fixed Position Layout
Project Layout
Line Layout
Product Layout
Line Layout
Shop layout
Process Layout
Functional Layout
Functional Layout
 Multiple Choice Multiple Answer
  Question 
Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view?
  Correct Answer 
Labour laws , Building codes , Policies regarding issue of licences
  Your Answer 
Labour laws , Building codes , Policies regarding issue of licences
 Select The Blank
  Question 
The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average.
  Correct Answer 
Acceptable quality level
  Your Answer 
Acceptable quality level
 Multiple Choice Multiple Answer
  Question 
Major contributors in the development of Control Charts, Sampling plan are
  Correct Answer 
F H Dodge , H G Roming , Walter Schewhart
  Your Answer 
F H Dodge , H G Roming , Walter Schewhart
 True/False
  Question 
Skill of labour force in a product type layout is usually higher than in the process type of layout
  Correct Answer 
False
  Your Answer 
True
 True/False
  Question 
Repetitive movements between work stations which are difficult to be traced on string diagrams can be conveniently shown on flow diagrams.
  Correct Answer 
False
  Your Answer 
True
 Select The Blank
  Question 
The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company.
  Correct Answer 
Inspection order
  Your Answer 
Job card
 Multiple Choice Multiple Answer
  Question 
Which of the following cases can be referred as operation in method study recording?
  Correct Answer 
Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic
  Your Answer 
Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic
 Select The Blank
  Question 
The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking.
  Correct Answer 
Condition monitoring
  Your Answer 
Overhauling
 True/False
  Question 
All activities lying on the non-critical paths must have total float and free float.
  Correct Answer 
False
  Your Answer 
False
 Select The Blank
  Question 
Work study is also called ________ study
  Correct Answer 
Time and Motion
  Your Answer 
Method
 Match The Following
Question
Correct Answer
Your Answer
Crash cost of an activity
Cc
Cc
Normal time of an activity
Tn
Tn
Crash time of activity
Tc
Tc
Normal cost of an activity
Cn
Cn
 Multiple Choice Multiple Answer
  Question 
Which are the advantages of suburban location?
  Correct Answer 
Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction
  Your Answer 
Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction
 True/False
  Question 
In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked out and inserted into a chart.
  Correct Answer 
True
  Your Answer 
False
 Multiple Choice Single Answer
  Question 
Which of the following is the criteria for the percentage defectives in the zone of the indecision?
  Correct Answer 
Lots having the percentage defective more than AQL but less than LPTD
  Your Answer 
Lots having the percentage defective less than AQL but more than LPTD
 Select The Blank
  Question 
The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________.
  Correct Answer 
Overtime working
  Your Answer 
Overtime working
 Multiple Choice Single Answer
  Question 
What do you mean by lowest possible direct cost required to complete an activity within it's crashed time?
  Correct Answer 
Crash cost
  Your Answer 
Crash cost
 Multiple Choice Single Answer
  Question 
In case of Batch Production which kind of labour is expected?
  Correct Answer 
Skilled in one specific Manufacturing Process
  Your Answer 
Semiskilled
 Multiple Choice Multiple Answer
  Question 
Which three of the following are causes of continuous upward pattern of Xbar-R control chart?
  Correct Answer 
Wear of tool , Abnormal rise in temperature , Accumulation of dirt
  Your Answer 
Wear of tool , Abnormal rise in temperature , Accumulation of dirt
 True/False
  Question 
Root cause of most of the breakdowns is failure of the lubrication system.
  Correct Answer 
True
  Your Answer 
True
 True/False
  Question 
It is not necessary to know spare time available on the non-critical path to allow a little delay for noncritical activity.
  Correct Answer 
False
  Your Answer 
False
 True/False
  Question 
MRP software generates time periodwise requiremetn of subassemblies
  Correct Answer 
True
  Your Answer 
True
 True/False
  Question 
In case of two handed process chart, the simultaneous activities of both hands are recorded opposite to each other on the chart.
  Correct Answer 
True
  Your Answer 
True
 Multiple Choice Single Answer
  Question 
What do you mean by CPM?
  Correct Answer 
Critical Path Method
  Your Answer 
Critical Path Method
 Multiple Choice Multiple Answer
  Question 
Which of the following are major inputs to scheduling?
  Correct Answer 
Overlapping of operations , Effective Capacity per work centre , Performance standards
  Your Answer 
Overlapping of operations , Effective Capacity per work centre , Performance standards
 Multiple Choice Multiple Answer
  Question 
Lack of material planning results in the following
  Correct Answer 
Over ordering , under ordering , stockouts
  Your Answer 
Over ordering , under ordering , stockouts
 Multiple Choice Single Answer
  Question 
What do you mean by the verification of object against predetermined standards of quality or quantity or both?
  Correct Answer 
Inspection
  Your Answer 
Inspection
 Multiple Choice Multiple Answer
  Question 
What are the advantages of templates over diagrams?
  Correct Answer 
Can be conveniently moved on the graph paper , Less laborious , Saves time
  Your Answer 
Can be conveniently moved on the graph paper , Less laborious , Unskilled person can do and analyze it
 True/False
  Question 
It would not affect the project completion time if non-critical activities take little loner time than planned.
  Correct Answer 
True
  Your Answer 
True
 Select The Blank
  Question 
The ________ is the probability that a good lot will be rejected by the sampling plan.
  Correct Answer 
Producer's risk
  Your Answer 
Producer's risk
 Multiple Choice Single Answer
  Question 
Any premise in which persons are employed for purpose of making any product/s is called
  Correct Answer 
Factory
  Your Answer 
Factory
 Select The Blank
  Question 
An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL .
  Correct Answer 
Rectangular
  Your Answer 
Bell
 Multiple Choice Single Answer
  Question 
Which is the right time to prepare stores issue order?
  Correct Answer 
When route sheet is ready
  Your Answer 
When route sheet is ready
 Multiple Choice Single Answer
  Question 
Which element of a network represents a task which has got a definite beginning and definite end?
  Correct Answer 
Activity
  Your Answer 
Activity
 Multiple Choice Single Answer
  Question 
Which kind of preventive inspection detects some defects in moving parts, internal cracks, and others , when machine is under preplanned shutdown?
  Correct Answer 
Internal inspection
  Your Answer 
Internal inspection
 Select The Blank
  Question 
Production Planning is a centralised activity which includes functions such as ________
  Correct Answer 
Scheduling
  Your Answer 
Dispatching
 Select The Blank
  Question 
The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable.
  Correct Answer 
Quality control
  Your Answer 
Quality control
 Select The Blank
  Question 
Goods after final inspection should accompany ________to enable dispatch department to identify and draw correct reference.
  Correct Answer 
Forwarding note
  Your Answer 
Forwarding note
 Multiple Choice Single Answer
  Question 
Who has introduced the useful concept of control chart in 1931?
  Correct Answer 
Walter Shewhart
  Your Answer 
Walter Shewhart
No comments: